CENTER PARCS

The Phase 2A extension at Center Parcs Longford Forest comprises the construction of 83 new holiday lodges within the existing forest resort. The development involves timber-framed accommodation units designed to integrate with the surrounding woodland environment.

 

Work on the project commenced on 6th May 2025 and is scheduled for completion in Q4 2026.

 

In addition to the installation of the 83 lodges, Connaught also undertook the groundworks package for a new Restaurant facility onsite at Center Parcs to support increased visitor capacity as part of the wider Phase 2 expansion.

 

Connaught were contracted to carry out a comprehensive civil engineering and groundworks package, including:

 

  • Enabling Works – installation of all haul roads, site compounds and chainlink fencing circa 3,000m.

  • Site preparation and clearance.

  • De-Watering systems for lifecycle of the project.

  • Bulk earthworks and excavation, including the excavation and onsite disposal of circa 14,000m³ of peat and stabilised material.

  • Concrete and foundation works, incorporating circa 3,700m³ of concrete.

  • Foul and storm drainage installation – circa 9,000m.

  • Watermain installation – circa 2,500m.

  • Electrical infrastructure installation – circa 4,000m.

  • Riverbed cleaning and overpumping works, carried out in conjunction with Inland Fisheries requirements.

  • Design and installation of gabion baskets for a Clear Water Vault.

  • Assistance with soil stabilisation works across the development.

  • Installation of pedestrian bridges.

  • Assistance with direct-buried cable and substation works.

  • Paving and hard landscaping works.

  • Soft landscaping and site reinstatement.

All associated works were done to the highest quality of works while maintaining high standards of health, safety and environmental issues on-site.

Project Name:

CENTER PARCS PHASE 2A                                                                                                       

 

Location:

CO LONGFORD

Main Contractor:

JOHN SISK & SONS

                                                                                                    

 

Date:

MAY 2025 TO DECEMBER 2026​

Center Parcs - 04.06.26
In partnership with Tusla
In partnership with Roscommon County Council
In partnership with SISK
In partnership with H&MV
In partnership with Direction For Our Times
In partnership with JJRhatigan
In partnership with Conack
In partnership with Highfield Energy
In partnership with IDA Ireland
In partnership with Stewart

Roscommon Head Office

Connaught Contractors Ltd

Connaught House

Castlerea Business Park

Henry Byrne Road

Castlerea

Co Roscommon

F45 RW29


Email: info@connaught.ie
Tel: (094) 962 2007

Galway Regional Office

Connaught Contractors Ltd

Office 9

Unit 18 Claregalway Corporate Park
Claregalway
Co Galway

H91 KFX3

 


Email: info@connaught.ie
Tel: (091) 451 001

Memberships and Accreditations

Connaught Contractors Ltd are pleased to have successfully completed our Stage 1 Audit to achieve and obtain certification for both ISO 9001:2015 Quality Management Systems & ISO 14001:2015 Environmental Management Systems Accreditation.

ISO accreditation

© 2026 by Connaught Contractors Ltd. All rights reserved.

Connaught logo
  • Facebook
  • LinkedIn
bottom of page